expand icon
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

Edition 2ISBN: 978-0072328882
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

Edition 2ISBN: 978-0072328882
Exercise 1
Give examples of problems that may arise when a designer fails to give adequate attention to the impact of a design selection on the cost or schedule during the construction phase.
Explanation
Verified
like image
like image
- Lack of attention to details in the plans may cause fitproblems in the field , which can lead to delays in work, increased costs, and claims from the construction contractor
- Inadequate attention to details during design can cause confusion during construction, including delays in work in the fieldand unnecessary rework.
- Some design selections can cause restrictions on the methods of construction that a contractor may choose, which can adversely affect the contractor's operations.
- Poor wording in the written specifications can cause misinterpretation of the requirements of the work to be performed, which can lead to poor quality work or costly change orders.
- Overly restrictive wording in the specifications may place restraints on the contractors operations and/or sequencing of construction work, which can affect costs and schedules.
- The selection of design alternatives can impact the procurement of major equipment required in a project, which can influence the scheduling of construction work.
- Requiring stringent inspection procedures in the plans and specifications that may interference in scheduling operations of the construction contractor.
- Designs that are poorly assembled can impair productivity of crafts, morale of workers on the job-site, and lead to legal claims against the designer and/or owner from the contractor.
- The quality of the design documents has a significant impact on the quality of construction and the long term maintenance and operations of the completed facility.