Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
Edition 2ISBN: 978-0072328882
Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
Edition 2ISBN: 978-0072328882 Exercise 6
Below are cost capacity curves for process units in a refinery. What is the estimated cost for a project that has a Process Unit B with a capacity of 4,000 barrels per day
Explanation
Locating the 4,000 barrels per day capa...