expand icon
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

Edition 2ISBN: 978-0072328882
book Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender cover

Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender

Edition 2ISBN: 978-0072328882
Exercise 5
As the project manager for a project, discuss options that might be considered for one of your team members who is having difficulty completing a design work package. Discuss options for each of the following situations: difficulty in defining the scope of work, difficulty in finding experienced personnel thatcan be assigned to tasks in the work package, and difficulty in estimating the time that it may take to complete the work.
Explanation
Verified
like image
like image

Difficulty in defining scope:
- Discus...