Edition 2ISBN: 978-0072328882 Exercise 4
You are in the bidding phase of a project and have received numerous inquiries about a particular part of the project. You have issued several addenda for clarification, but still continue to receive questions.
(A) What is your assessment of the possible causes for the numerous questions from bidders
(B) What could you, as project manager, have done that might have prevented the problem
(C) How would you handle the problem, considering you are now in the bidding phase
(A) What is your assessment of the possible causes for the numerous questions from bidders
(B) What could you, as project manager, have done that might have prevented the problem
(C) How would you handle the problem, considering you are now in the bidding phase
Explanation
(A) Possible Causes:
- Errors were mad...