Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley
Edition 1ISBN: 978-0077426903
Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley
Edition 1ISBN: 978-0077426903 Exercise 22
Swoosh Snowboard Company must set up an assembly line for snowboards.Forecasts show that 600 units per day should be produced.The plant operates two eight-hour shifts each day and runs the line continuously during both shifts.The tasks required, task times, and precedence relationships are as follows:
a.Draw the precedence diagram.
b.What is the takt time?
c.What are the theoretical number of workstations
d.Assign the tasks to the workstations to balance the line using the longest operating time rule.
e.What is the efficiency of the balanced line?

b.What is the takt time?
c.What are the theoretical number of workstations
d.Assign the tasks to the workstations to balance the line using the longest operating time rule.
e.What is the efficiency of the balanced line?
Explanation
The overall cycle time of an assembly li...