Complete the MRP record for a bicycle frame using a L4L lot-sizing strategy.Considering the lead time, where should scheduled receipts be shown? Repeat using a fixed order quantity of 100 frames.Again, show scheduled receipts.Compare and contrast the results.What are the benefits and drawbacks to each approach? 

Explanation
Create material requirements plan using ...