expand icon
book Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley cover

Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley

Edition 1ISBN: 978-0077426903
book Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley cover

Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley

Edition 1ISBN: 978-0077426903
Exercise 21
Given the following table of precedence relationships for a portion of a house-building project: Given the following table of precedence relationships for a portion of a house-building project:   a.Draw a network diagram for this project and identify the critical path. b.What assumptions may have been made in the development of the time estimates? c.What will happen to the project if the materials needed for the frame preassembly are not available until the second day of the project? What if the materials were delayed until the tenth day? d.Do you see any potential resource conflicts in this schedule? Will there be any incompatible tasks occurring simultaneously? a.Draw a network diagram for this project and identify the critical path.
b.What assumptions may have been made in the development of the time
estimates?
c.What will happen to the project if the materials needed for the frame preassembly are not available until the second day of the project? What if the materials were delayed until the tenth day?
d.Do you see any potential resource conflicts in this schedule? Will there be any incompatible tasks occurring simultaneously?
Explanation