Consider the supply chain planning implementation project depicted in Figure 16S-1.Suppose that the client has offered a $4,000 bonus to us if we can complete the project seven working days early.Based upon the crash cost information provided in Table 16S-1, would you accept the client's proposal? By how many days could you profitably shorten the project?
(In Reference Figure 16S-1)
(In Reference Table 16S-1)
(In Reference Figure 16S-1)

(In Reference Table 16S-1)

Explanation
The given data about the project is as s...