expand icon
book Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley cover

Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley

Edition 1ISBN: 978-0077426903
book Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley cover

Managing Operations Across the Supply Chain 1st Edition by Morgan Swink,Steven Melnyk,Bixby Cooper, Janet Hartley

Edition 1ISBN: 978-0077426903
Exercise 18
Consider the following software development plan. Consider the following software development plan.    a.The client has asked for an estimated completion date.What would you tell her? b.The client would like to have the completed software in 37 weeks.What is the likelihood that the critical path will be completed in that time frame? c.The client has just asked if it would be possible to have the completed software in 36 weeks.What is the likelihood the project will be completed in that time frame? d.The client wants to know if it would be possible to complete the project in 33 weeks.What is the probability of meeting the client's demand? e.You are concerned about the accuracy of your calculations because the paths are not independent.What is the likelihood that all of the coding activities will be completed on time?
a.The client has asked for an estimated completion date.What would you tell her?
b.The client would like to have the completed software in 37 weeks.What is the likelihood that the critical path will be completed in that time frame?
c.The client has just asked if it would be possible to have the completed software in 36 weeks.What is the likelihood the project will be completed in that time frame?
d.The client wants to know if it would be possible to complete the project in 33 weeks.What is the probability of meeting the client's demand?
e.You are concerned about the accuracy of your calculations because the paths are not independent.What is the likelihood that all of the coding activities will be completed on time?
Explanation
Verified
like image
like image

a)
Enter the values in the excel sheet a...