expand icon
book Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins cover

Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins

Edition 7ISBN: 978-0077733773
book Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins cover

Cost Management: A Strategic Emphasis 7th Edition by Edward Blocher,David Stout ,Paul Juras,Gary Cokins

Edition 7ISBN: 978-0077733773
Exercise 59
Cost Estimation; High-Low Method Horizon BP in Antelope Park, Alaska, has noticed that utility bills are substantially higher when the average monthly temperature is colder. The only thing in the shop that uses natural gas is the furnace. Because of prevailing low temperatures, the furnace is used every month of the year (though less in the summer months and very little in August). Everything else in the shop runs on electricity, and electricity use is fairly constant throughout the year.
For a year, Horizon has been recording the average daily temperature and the cost of its monthly utility bills for natural gas and electricity.
Cost Estimation; High-Low Method Horizon BP in Antelope Park, Alaska, has noticed that utility bills are substantially higher when the average monthly temperature is colder. The only thing in the shop that uses natural gas is the furnace. Because of prevailing low temperatures, the furnace is used every month of the year (though less in the summer months and very little in August). Everything else in the shop runs on electricity, and electricity use is fairly constant throughout the year. For a year, Horizon has been recording the average daily temperature and the cost of its monthly utility bills for natural gas and electricity.     Required Use the high-low method to estimate utility cost for the upcoming months of January and February. The forecast for January is a near record average temperature of 5°F; temperatures in February are expected to average 40°F.
Required Use the high-low method to estimate utility cost for the upcoming months of January and February. The forecast for January is a near record average temperature of 5°F; temperatures in February are expected to average 40°F.
Explanation
Verified
like image
like image

High-Low method
High-low method is used...