Assume that the project in Problem 3 has the following activity times (in months):
a. Find the critical path.
b. The project must be completed in 1½ years. Do you anticipate difficulty in meeting the deadline? Explain.

a. Find the critical path.
b. The project must be completed in 1½ years. Do you anticipate difficulty in meeting the deadline? Explain.