Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
a. Draw a project network.
b. What are the critical activities?
c. What activity has the most slack time?
d. Will the project be completed by September 1?

a. Draw a project network.
b. What are the critical activities?
c. What activity has the most slack time?
d. Will the project be completed by September 1?
Explanation
a)Draw a project network given that the ...