expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
Exercise 6
Suppose that the following estimates of activity times (in weeks) were provided for the network shown in Problem 6: Suppose that the following estimates of activity times (in weeks) were provided for the network shown in Problem 6:    What is the probability that the project will be completed a. Within 21 weeks? b. Within 22 weeks? c. Within 25 weeks?
What is the probability that the project will be completed
a. Within 21 weeks?
b. Within 22 weeks?
c. Within 25 weeks?
Explanation
Verified
like image
like image

a)For computing the probability that the...