expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
Exercise 7
Davison Construction Company is building a luxury lakefront home in the finger region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-weck (approximately 10-month) completion date requested by the owner The Davison project manager prepared the following project network: Davison Construction Company is building a luxury lakefront home in the finger region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-weck (approximately 10-month) completion date requested by the owner The Davison project manager prepared the following project network:    Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows:    a. Find the critical path. b. What is the expected project completion time? c. What is the probability the project can be completed in the 44 weeks as requested by the owner? d. What is die probability the building project could run more than 3 months late? Use 57 weeks for this calculation. e. What should the construction company tell the owner?
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows: Davison Construction Company is building a luxury lakefront home in the finger region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-weck (approximately 10-month) completion date requested by the owner The Davison project manager prepared the following project network:    Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows:    a. Find the critical path. b. What is the expected project completion time? c. What is the probability the project can be completed in the 44 weeks as requested by the owner? d. What is die probability the building project could run more than 3 months late? Use 57 weeks for this calculation. e. What should the construction company tell the owner?
a. Find the critical path.
b. What is the expected project completion time?
c. What is the probability the project can be completed in the 44 weeks as requested by the owner?
d. What is die probability the building project could run more than 3 months late? Use 57 weeks for this calculation.
e. What should the construction company tell the owner?
Explanation
Verified
like image
like image

a)For identifying the critical path, pro...