The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practise is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows:
a. Draw a project network.
b. Develop an activity schedule.
c. What are the critical activities, and what is the expected project completion time?
d. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?

a. Draw a project network.
b. Develop an activity schedule.
c. What are the critical activities, and what is the expected project completion time?
d. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?
Explanation
a)Draw a project network for the activit...
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255