The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources. Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates (in weeks) are
a. Develop an activity schedule for this project and identify the critical path activities.
b. What is the probability that the project will be completed so that Landon Corporation may introduce new product within 25 weeks? Within 30 weeks?

The activity time estimates (in weeks) are

a. Develop an activity schedule for this project and identify the critical path activities.
b. What is the probability that the project will be completed so that Landon Corporation may introduce new product within 25 weeks? Within 30 weeks?
Explanation
Compute the expected activity completion...