Edition 13ISBN: 978-1439043271 Exercise 20
Consider the following project network and activity times (in days):
The crashing data for this project are as follows:
a. Find the critical path and the expected project completion time.
b. What is the total project cost using the normal times?


The crashing data for this project are as follows:

a. Find the critical path and the expected project completion time.
b. What is the total project cost using the normal times?
Explanation
a)To find the critical path and activity...