Exercise 16
Do you understand PERT charts? Refer back to Figure 13-11 Do you understand PERT charts? Refer back to Figure 13-11   and answer the following questions: a. Which activity or activities must be completed before activity C can begin? b. Which activity or activities must be completed before activity G can begin? c. Which activity or activities must be completed before activity J can begin? d. What are the five paths through the network? Which one is the critical path? e. What is the earliest projected start time for activity F? f. What is the earliest projected start time for activity G? g. What is the latest time that activity J can begin without delaying the entire project? h. What is the latest time that activity G can begin without delaying the entire project? i. What is the slack time for activity G? (Hint: it's the difference between the early and late start times.) and answer the following questions:
a. Which activity or activities must be completed before activity C can begin?
b. Which activity or activities must be completed before activity G can begin?
c. Which activity or activities must be completed before activity J can begin?
d. What are the five paths through the network? Which one is the critical path?
e. What is the earliest projected start time for activity F?
f. What is the earliest projected start time for activity G?
g. What is the latest time that activity J can begin without delaying the entire project?
h. What is the latest time that activity G can begin without delaying the entire project?
i. What is the slack time for activity G? (Hint: it's the difference between the early and late start times.)
Explanation
Verified
like image
like image

(a) B activity must be completed before ...