All of These Describe Contemporary Methods of Risk Prioritization in Project

Question 40

Multiple Choice

All of these describe contemporary methods of risk prioritization in project management EXCEPT: 


A)  Risk prioritization is generally based on the probability of occurrence and severity of impact of each identified risk. 
B)  Some organizations place a higher priority on risks that are likely to happen soon. 
C)  Some organizations call attention to the risks that are difficult to detect. 
D)  Results of quantitative risk analysis are used for clarification purposes and are typically not documented in the risk register.

Correct Answer:

verifed

Verified