Multiple Choice
A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3,a complexity risk of 0.7,and a dependency risk of 0.8.The probability of failure is:
A) Less than or equal to 0.3.
B) Greater than 0.3 but less than or equal to 0.55.
C) Greater than 0.56 but less than or equal to 0.89.
D) Greater than or equal to 0.9.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: The professor wore both a belt and
Q8: Which of these statements about the project
Q9: Risk cannot be transferred because ultimately your
Q10: The programming division at ABC decides to
Q11: The PRAM model for risk management proposes
Q13: What are fixed-price contracts and liquidated damages?
Q14: The expected cost of an item that
Q15: Contingency reserves require a construction company to
Q16: The project team toiled long into
Q17: Twenty-thousand dollars was budgeted for the office