A Project Team Assesses Their Primary Risk Factor's Probability of Failure

Question 12

Multiple Choice

A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3,a complexity risk of 0.7,and a dependency risk of 0.8.The probability of failure is:


A) Less than or equal to 0.3.
B) Greater than 0.3 but less than or equal to 0.55.
C) Greater than 0.56 but less than or equal to 0.89.
D) Greater than or equal to 0.9.

Correct Answer: