Solved

Use the Earned Value Table for Project Makeready to Calculate

Question 31

Multiple Choice

Use the earned value table for Project Makeready to calculate their schedule performance index.  Activity 7142128354249 plan 8 Complete  Install fixtures 325250575100% Refinish floors 55085635100% Replace doors 350275625100% Complete tiling 1,2005651,76580% Install back door 8752251,10070% Landscaping 20035055025% Monthly Plan 3258004351,4751,4404253505,250 Monthly Act 5505505501,1001,6505501,100\begin{array} { | l | l | l | l | l | l | l | l | l | l | } \hline \text { Activity } & 7 & 14 & 21 & 28 & 35 & 42 & 49 & \text { plan } & 8 \text { Complete } \\\hline \text { Install fixtures } & 325 & 250 & & & & & & 575 & 100 \% \\\hline \text { Refinish floors } & & 550 & 85 & & & & & 635 & 100 \% \\\hline \text { Replace doors } & & & 350 & 275 & & & & 625 & 100 \% \\\hline \text { Complete tiling } & & & & 1,200&565 & & & 1,765 & 80 \% \\\hline \text { Install back door } & & & & & 875 & 225 & & 1,100&70 \% \\\hline \text { Landscaping } & & & & & & 200 & 350 & 550 & 25 \% \\\hline \text { Monthly Plan } & 325 & 800 & 435 & 1,475 & 1,440&425 & 350 & 5,250 & \\\hline \text { Monthly Act } & 550 & 550 & 550 & 1,100 & 1,650 & 550 & 1,100 & & \\\hline\end{array}


A) 1.46
B) 0.68
C) 0.79
D) 1.26

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions