Multiple Choice
Manufacturing Mates produces special-order tiles for organizations.The company reported that they produced 250 batches of tile and the setup time per batch was 2 hours.Compute the total setup hours.
A) 300 setup hours
B) 400 setup hours
C) 500 setup hours
D) 600 setup hours
E) 700 setup hours
Correct Answer: