Housing Construction Company (HCC) has agreed to build a housing project for the city of New York. On January 1st, 2006 the company and the city agreed on the following terms, the construction should take no more than 3 years, HCC would be paid a total of $150 million for the project; the $150 million would be paid: 3 payments of $50 million each at the end of year 2006, 2007 and 2008. HCC expects contractions costs to be $50 million in year 2006, $50 million in year 2007, and $10 million in year 2008.
a. If HCC uses the completed contract method, what revenues and expenses would HCC recognize in year 2006, 2007, and 2008?
b. If HCC uses the percentage of completion method, what revenues and expenses would HCC recognize in year 2006, 2007, and 2008?
c. Show the balance on the construction-in-process account at the end of 2006, 2007, and 2008 (prior to the completion of the project) using both the completed contract and the percentage of completion methods?
Correct Answer:

Verified
a. Year 1 and Year 2: no revenues and ex...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q7: The capitalization of interest cost during construction:<br>A)increases
Q7: Windsor Company has net temporary differences
Q8: Employee stock options (ESOs) usually constitute a
Q8: The table below shows the differences
Q11: If a company that normally expenses advertising
Q13: When a company disposes of a segment
Q27: Deferred taxes arise due to temporary timing
Q29: Some items appear on a company's income
Q33: A company that capitalizes costs, rather than
Q76: The capitalization of interest costs during construction