Deck 6: Allocating Resources to the Project
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/46
Play
Full screen (f)
Deck 6: Allocating Resources to the Project
1
Often it is beneficial to crash activities NOT on the critical path.
False
2
When crashing a task,the usual assumption is that a task is crashed the full amount or none at all.
False
3
For resources that are consumed when used,the problem is which project gets to use the resource first and which must wait.
False
4
Trade-offs must be made in order to optimize the use of limited resources.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
5
Good PM are able to estimate project task times with absolute certainty
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
6
If resources were not scarce,the resource allocation problem would be concerned solely with cost minimization.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
7
The time to complete a task with normal or standard-practice resource usage is referred to as the crash duration.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
8
If resources were not scarce,the resource allocation problem would be concerned solely with profit maximization.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
9
The amount of resources a project can use depends in part on the timing of the allocation.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
10
It is considered good management to crash the least costly activities before the more costly ones.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
11
The variance of the normal time can be quite different from the variance of the crash time.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
12
Fast-tracking a project is used primarily in the pharmaceutical industry.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
13
When the work is routine,fast-tracking rarely causes serious problems.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
14
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
15
All projects are carried out under conditions of uncertainty.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
16
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
17
All tasks can be crashed to some extent.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
18
Projects often compete with each other for the same resources.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
19
The CPM method cannot be used when task durations are probabilistic.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
20
A project that must be completed by a fixed time is referred to as resource constrained.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
21
The primary cause of concern in resource allocation is
A) labor cost
B) resource scarcity
C) lack of solution methodologies
D) parallel activities
E) equipment downtime
A) labor cost
B) resource scarcity
C) lack of solution methodologies
D) parallel activities
E) equipment downtime
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
22
MSP allows the PM to create an individual availability calendar for each resource on the project
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
23
A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
24
Allocating specific,limited resources to specific activities is called
A) resource allocation
B) resource leveling
C) resource tracking
D) expediting a project
E) crashing a project
A) resource allocation
B) resource leveling
C) resource tracking
D) expediting a project
E) crashing a project
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
25
A task's duration is a function of both the amount of labor required to complete the task as well as the calendar time required to complete it.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
26
Pools of like workers are most useful when labor is subdivided into highly specialized subtasks.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
27
Applying "line balancing" techniques to balance the capacity of a project typically yields significant benefits.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
28
A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
29
One limitation of MSP is that all resources must share the same availability calendar.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
30
The task duration with standard-practice resource usage is referred to as the
A) expected task duration
B) nominal task duration
C) crash duration
D) normal task duration
E) planned task duration
A) expected task duration
B) nominal task duration
C) crash duration
D) normal task duration
E) planned task duration
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
31
The as late as possible priority rule is considered the standard scheduling rule.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
32
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project's duration?
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
33
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
34
Crashing refers to
A) expediting the project so as to minimizing the total cost of completing the project.
B) expediting the project so as to minimizing the number of activities in the project
C) expediting the project so as to completing the project by a specified time.
D) all of the above
E) none of the above.
A) expediting the project so as to minimizing the total cost of completing the project.
B) expediting the project so as to minimizing the number of activities in the project
C) expediting the project so as to completing the project by a specified time.
D) all of the above
E) none of the above.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
35
A task has a normal duration of 9 days and a crash duration of 7 days.Its normal cost is $40 and its crash cost is $100.What is the crash cost per day?
A) $140
B) $70
C) $50
D) $40
E) $30
A) $140
B) $70
C) $50
D) $40
E) $30
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
36
A project that must be completed by a specific time is considered
A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
37
Starting the building phase before the design and planning phases is called
A) operations overlapping
B) concurrent engineering
C) fast-tracking
D) concurrent construction
E) construction overlapping
A) operations overlapping
B) concurrent engineering
C) fast-tracking
D) concurrent construction
E) construction overlapping
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
38
Which of the following is NOT considered a resource
A) Money
B) People
C) Equipment
D) Material
E) All of the above
A) Money
B) People
C) Equipment
D) Material
E) All of the above
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
39
Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
40
In general,steady state demand for human resources is highly desirable.
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
41
The safety time added to chains other than the critical chain is called
A) feeding buffer
B) project buffer
C) path buffer
D) critical buffer
E) team buffer
A) feeding buffer
B) project buffer
C) path buffer
D) critical buffer
E) team buffer
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
42
The practice of assigning project team members to multiple projects is called
A) concurrent engineering
B) parallel activities
C) fast-tracking
D) project crashing
E) multitasking
A) concurrent engineering
B) parallel activities
C) fast-tracking
D) project crashing
E) multitasking
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
43
Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?
A) schedule inflation
B) schedule progression
C) schedule efficacy
D) schedule efficiency
E) schedule slippage
A) schedule inflation
B) schedule progression
C) schedule efficacy
D) schedule efficiency
E) schedule slippage
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
44
Which of the following is NOT commonly used to help select a priority rule?
A) schedule slippage
B) resource utilization
C) in-process inventory
D) cost overruns
E) all of the above are used
A) schedule slippage
B) resource utilization
C) in-process inventory
D) cost overruns
E) all of the above are used
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
45
A project that must be completed with in the specified performance requirements is considered
A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
Unlock Deck
Unlock for access to all 46 flashcards in this deck.
Unlock Deck
k this deck
46
According to research,the best overall priority rule is
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor