Exercise 13
The following tasks are required to assemble a product. The following tasks are required to assemble a product.   The company believes that the market rate of demand for the product requires an output of 12 per hour. Calculate the takt time and then use the longest operating time (LOT) heuristic to assign tasks to workstations. The company believes that the market rate of demand for the product requires an output of 12 per hour. Calculate the takt time and then use the longest operating time (LOT) heuristic to assign tasks to workstations.
Explanation
Verified
like image
like image

Line balancing:
The process assigning t...