Exercise 17
Calculate the process design capacity, available capacity, actual capacity, capacity utilization, efficiency, and output gap for a process that has been designed to produce 200 units per hour with a scrap rate of 0.5%, inherent inefficiencies of 4%, and actual output of 180 units per hour.
Explanation
Verified
like image
like image

Modeling capacity:
Modeling capacity is...