
Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb
Edition 1ISBN: 9780134110219
Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb
Edition 1ISBN: 9780134110219 Exercise 19
Three time estimates for a task in a project are as follows:
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time = 15 weeks
Calculate the expected task completion time.
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time = 15 weeks
Calculate the expected task completion time.
Explanation
Estimated task completion time:
Estimat...
Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255