Three time estimates for a task in a project are as follows:
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time - 15 weeks
Calculate the expected task variance.
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time - 15 weeks
Calculate the expected task variance.
Explanation
Task variance: