A project has a task with the following task time estimates:
Pessimistic completion time = 18 weeks
Most likely completion time = 15 weeks
Optimistic completion time = 7 weeks.
What is the variance for the task?
Explanation
Verified
like image
like image

Task variance:
Task variance is helps t...