Exercise 8
The optimistic, most likely, and pessimistic times for the tasks making up a project are as follows. Use the data to compute the expected completion time and variance for each task. The optimistic, most likely, and pessimistic times for the tasks making up a project are as follows. Use the data to compute the expected completion time and variance for each task.
Explanation
Verified
like image
like image

Estimated task completion time:
Estimat...