The _____________ chart graphically displays the scheduling of tasks required to complete a project. (a) exception
(b) Taylor
(c) Gantt
(d) after-action
(b) Taylor
(c) Gantt
(d) after-action
Explanation
.
Explanation:
Option (c) is correct...