In a CPM/PERT analysis the focus is on _____________ and the event that link them together with the finished project. (a) costs, budgets
(b) activities, sequences
(c) timetables, budgets
(d) goals, costs
(b) activities, sequences
(c) timetables, budgets
(d) goals, costs
Explanation
.
Explanation:
Option (b) is correct...