expand icon
book Operations and Supply Chain Management 14th Edition by Robert Jacobs,Richard Chase cover

Operations and Supply Chain Management 14th Edition by Robert Jacobs,Richard Chase

Edition 14ISBN: 978-0077535179
book Operations and Supply Chain Management 14th Edition by Robert Jacobs,Richard Chase cover

Operations and Supply Chain Management 14th Edition by Robert Jacobs,Richard Chase

Edition 14ISBN: 978-0077535179
Exercise 9
What is the efficiency of an assembly line that has 25 workers and a cycle time of 45 seconds? Each unit produced on the line has 16 minutes of work that needs to be completed based on a time study completed by engineers at the factory.
Explanation
Verified
like image
like image

A layout, in which the jobs are arranged...

close menu
Operations and Supply Chain Management 14th Edition by Robert Jacobs,Richard Chase
cross icon