In Problem, suppose that the demand for personal computers increased each month, as follows:
In Problem, suppose that the demand for personal computers increased each month, as follows:    In addition to the regular production capacity of 300 units per month, PM Computer Services can also produce an additional 200 computers per month by using overtime. Overtime production adds 20% to the cost of a personal computer. Determine a production schedule for PM that will minimize total cost. Problem  PM Computer Services produces personal computers from component parts it buys on the open market. The company can produce a maximum of 300 personal computers per month. PM wants to determine its production schedule for the first 6 months of the new year. The cost to produce a personal computer in January will be $1,200. However, PM knows the cost of component parts will decline each month so that the overall cost to produce a PC will be 5% less each month. The cost of holding a computer in inventory is $15 per unit per month. Following is the demand for the company's computers each month:    Determine a production schedule for PM that will minimize total cost. In addition to the regular production capacity of 300 units per month, PM Computer Services can also produce an additional 200 computers per month by using overtime. Overtime production adds 20% to the cost of a personal computer.
Determine a production schedule for PM that will minimize total cost.
Problem
PM Computer Services produces personal computers from component parts it buys on the open market. The company can produce a maximum of 300 personal computers per month. PM wants to determine its production schedule for the first 6 months of the new year. The cost to produce a personal computer in January will be $1,200. However, PM knows the cost of component parts will decline each month so that the overall cost to produce a PC will be 5% less each month. The cost of holding a computer in inventory is $15 per unit per month. Following is the demand for the company's computers each month:
In Problem, suppose that the demand for personal computers increased each month, as follows:    In addition to the regular production capacity of 300 units per month, PM Computer Services can also produce an additional 200 computers per month by using overtime. Overtime production adds 20% to the cost of a personal computer. Determine a production schedule for PM that will minimize total cost. Problem  PM Computer Services produces personal computers from component parts it buys on the open market. The company can produce a maximum of 300 personal computers per month. PM wants to determine its production schedule for the first 6 months of the new year. The cost to produce a personal computer in January will be $1,200. However, PM knows the cost of component parts will decline each month so that the overall cost to produce a PC will be 5% less each month. The cost of holding a computer in inventory is $15 per unit per month. Following is the demand for the company's computers each month:    Determine a production schedule for PM that will minimize total cost. Determine a production schedule for PM that will minimize total cost.
Explanation
Verified
like image
like image

First, put together the linear programmi...