Introduction to Management Science 12th Edition by Bernard Taylor
Edition 12ISBN: 978-0133778847
Introduction to Management Science 12th Edition by Bernard Taylor
Edition 12ISBN: 978-0133778847 Exercise 30
Consider the network in Problem, but with the following new time estimates for each activity:
Determine the following:
a. Expected activity times
b. Earliest activity times
c. Latest activity times
d. Activity slack
e. Critical path
f. Expected project duration and variance
Problem
Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration.


a. Expected activity times
b. Earliest activity times
c. Latest activity times
d. Activity slack
e. Critical path
f. Expected project duration and variance
Problem
Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration.

Explanation
A project requires planning, scheduling ...
Introduction to Management Science 12th Edition by Bernard Taylor
Why donât you like this exercise?
Other Minimum 8 character and maximum 255 character