Exercise 13
A customer places an order on January 1, 2013. Ten days later that order is received by the manufacturing department. Fifteen days later, the order is put into production. Processing (manufacturing) time is 20 days for this order. The completed order is then shipped 10 days later. For this order, what was the total customer-response time (CRT)
Explanation
Verified
like image
like image

Customer-Response Time (CRT): It is the ...