Another term for "activity on node," the most commonly used technique for constructing a schedule model, is:
A) precedence diagramming method (PDM)
B) arrow diagramming method (ADM)
C) activity on arrow (AOA)
D) activity attribute method (AAM)
A) precedence diagramming method (PDM)
B) arrow diagramming method (ADM)
C) activity on arrow (AOA)
D) activity attribute method (AAM)
Explanation
Activity on Node (AON ) is the most comm...