Exercise 2
Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?
Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?     a. Schedule variance (SV) b. Cost variance (CV) c. Schedule performance index (SPI) d. Cost performance index (CPI) e. Estimate to complete (ETC-first method) f. Estimate to complete (ETC-second method) g. Estimate at completion (EAC) h. To-complete performance index (TCPI)
a. Schedule variance (SV)
b. Cost variance (CV)
c. Schedule performance index (SPI)
d. Cost performance index (CPI)
e. Estimate to complete (ETC-first method)
f. Estimate to complete (ETC-second method)
g. Estimate at completion (EAC)
h. To-complete performance index (TCPI)
Explanation
Verified
like image
like image

By extracting the information :
blured image blured image blured image blured image Par...