Exercise 3
A project manager has just learned that the schedule performance index (SPI) for his project is 85 percent. The calculation of the cost performance index (CPI) is 107 percent. How would you describe this project both in terms of budget and schedule?
Explanation
Verified
like image
like image

Evaluation of project in terms of budget...