expand icon
book Cornerstones of Managerial Accounting 4th Edition by Maryanne Mowen, Don Hansen, Dan Heitger cover

Cornerstones of Managerial Accounting 4th Edition by Maryanne Mowen, Don Hansen, Dan Heitger

Edition 4ISBN: 978-0324380767
book Cornerstones of Managerial Accounting 4th Edition by Maryanne Mowen, Don Hansen, Dan Heitger cover

Cornerstones of Managerial Accounting 4th Edition by Maryanne Mowen, Don Hansen, Dan Heitger

Edition 4ISBN: 978-0324380767
Exercise 51
( Appendix 12A ) Calculating Manufacturing Cycle Efficiency
Indy Company has the following data for one of its manufacturing plants:
Maximum units produced in a quarter (3-month period): 250,000 units
Actual units produced in a quarter (3-month period): 200,000 units
Productive hours in one quarter: 25,000 hours
Refer to the information for Indy Company above. The actual cycle time for Indy Company is 7.5 minutes and the theoretical cycle time is 6 minutes.
Required:
1. Calculate the amount of processing time and the amount of nonprocessing time.
2. Calculate the MCE.
Explanation
Verified
like image
like image

• Cycle time is the length of time it ta...

close menu
Cornerstones of Managerial Accounting 4th Edition by Maryanne Mowen, Don Hansen, Dan Heitger
cross icon