Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
Edition 2ISBN: 978-0072328882
Instructor's Manual to Accompany Project Management for Engineering and Construction 2nd Edition by Oberlender
Edition 2ISBN: 978-0072328882 Exercise 2
The EPC project shown in Appendix A has an original planned schedule of 17 months with a budget, excluding contingency, of $3,053,150. Below are update reports for the first 8 months of the project.
Explanation
Analysis of Month #1:
The status repor...