As part of a quality improvement initiative. Consolidated Electronics employees complete a three-day training program on teaming and a two-day training program on problem solving. The manager of quality improvement has requested that at least 8 training programs on teaming and at least 10 training programs on problem solving be offered during the next six months. In addition, senior-level management has specified that at least 25 training programs must be offered during this period. Consolidated Electronics uses a consultant to teach the training programs on teaming costs $10,000 and each training program on problem solving costs $8000.
a. Formulate a linear programming model that can be used to determine the number of training that should be offered in order to minimize total cost.
b. Graph the feasible region.
c. Determine the coordinates of each extreme point.
d. Solve for the minimum cost solution.
a. Formulate a linear programming model that can be used to determine the number of training that should be offered in order to minimize total cost.
b. Graph the feasible region.
c. Determine the coordinates of each extreme point.
d. Solve for the minimum cost solution.
Explanation
Linear programming:
Linear programming ...