expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
Exercise 17
Assume that the project in Problem 3 has the following activity times (in months): Assume that the project in Problem 3 has the following activity times (in months):    a. Find the critical path. b. The project must be completed in 1½ years. Do you anticipate difficulty in meeting the deadline? Explain.
a. Find the critical path.
b. The project must be completed in 1½ years. Do you anticipate difficulty in meeting the deadline? Explain.
Explanation
Verified
like image
like image

a)Construct a project network given the ...

close menu
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
cross icon