Consider the following project network and activity times (in weeks):
a. Identify the critical path.
b. How much time will be needed to complete this project?
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?
e. What is the schedule for activity E?


a. Identify the critical path.
b. How much time will be needed to complete this project?
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?
e. What is the schedule for activity E?
Explanation
a)Identify the critical path in the netw...