Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows:
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:
a. Formulate a linear programming model that can be used to make the crashing decisions for this project.
b. Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of melting the 16-week completion time?
c. Develop a complete activity schedule based on the crashed activity times.


The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:

a. Formulate a linear programming model that can be used to make the crashing decisions for this project.
b. Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of melting the 16-week completion time?
c. Develop a complete activity schedule based on the crashed activity times.
Explanation
Situation:
Company N wants to install a...
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255