expand icon
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
book An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin cover

An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin

Edition 13ISBN: 978-1439043271
Exercise 15
A project has four activities (A. B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: A project has four activities (A. B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:      a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. b. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks. c. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks or less. A project has four activities (A. B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:      a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. b. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks. c. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks or less.
a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
b. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks.
c. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks or less.
Explanation
Verified
like image
like image

It is given that the project has four ac...

close menu
An Introduction to Management Science 13th Edition by David Anderson,Dennis Sweeney ,Thomas Williams ,Jeffrey Camm, Kipp Martin
cross icon