
Smith and Roberson's Business Law 16th Edition by Richard Mann,Barry Roberts
Edition 16ISBN: 978-1285428253
Smith and Roberson's Business Law 16th Edition by Richard Mann,Barry Roberts
Edition 16ISBN: 978-1285428253 Exercise 6
Daniel agreed to erect an apartment building for Steven for $12 million and that Daniel would suffer a deduction of $12,000 per day for every day of delay. Daniel was twenty days late in finishing the job, losing ten days because of a strike and ten days because the material suppliers were late in furnishing materials. Daniel claims that he is entitled to payment in full (a) because the agreement as to $12,000 a day is a penalty and (b) because Steven has not shown that he has sustained any damage. Discuss each contention and decide.
Explanation
As per the case, Mr. D will not recover ...
Smith and Roberson's Business Law 16th Edition by Richard Mann,Barry Roberts
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255