Exam 11: Cash Flow Estimation and Risk Analysis

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

As a member of UA Corporation's financial staff, you must estimate the Year 1 cash flow for a proposed project with the following data. What is the Year 1 cash flow?

(Multiple Choice)
4.8/5
(37)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(41)

Foley Systems is considering a new investment whose data are shown below. The equipment would be depreciated on a straight-line basis over the project's 3-year life, would have a zero salvage value, and would require some additional working capital that would be recovered at the end of the project's life. Revenues and other operating costs are expected to be constant over the project's life. What is the project's NPV? (Hint: Cash flows are constant in Years 1 to 3.)

(Multiple Choice)
4.9/5
(45)

Sensitivity analysis measures a project's stand-alone risk by showing how much the project's NPV (or IRR) is affected by a small change in one of the input variables, say sales. Other things held constant, with the size of the independent variable graphed on the horizontal axis and the NPV on the vertical axis, the steeper the graph of the relationship line, the more risky the project, other things held constant.

(True/False)
4.8/5
(31)

Dalrymple Inc. is considering production of a new product. In evaluating whether to go ahead with the project, which of the following items should NOT be explicitly considered when cash flows are estimated?

(Multiple Choice)
4.9/5
(39)

You work for Whittenerg Inc., which is considering a new project whose data are shown below. What is the project's Year 1 cash flow?

(Multiple Choice)
4.9/5
(49)

Any cash flows that can be classified as incremental to a particular project--i.e., results directly from the decision to undertake the project--should be reflected in the capital budgeting analysis.

(True/False)
4.8/5
(39)

Estimating project cash flows is generally the most important, but also the most difficult, step in the capital budgeting process. Methodology, such as the use of NPV versus IRR, is important, but less so than obtaining a reasonably accurate estimate of projects' cash flows.

(True/False)
4.8/5
(42)

TexMex Food Company is considering a new salsa whose data are shown below. The equipment to be used would be depreciated by the straight-line method over its 3-year life and would have a zero salvage value, and no new working capital would be required. Revenues and other operating costs are expected to be constant over the project's 3-year life. However, this project would compete with other TexMex products and would reduce their pre-tax annual cash flows. What is the project's NPV? (Hint: Cash flows are constant in Years 1-3.)

(Multiple Choice)
5.0/5
(41)

The primary advantage to using accelerated rather than straight-line depreciation is that with accelerated depreciation the total amount of depreciation that can be taken, assuming the asset is used for its full tax life, is greater.

(True/False)
4.8/5
(33)

Suppose a firm's CFO thinks that an externality is present in a project, but that it cannot be quantified with any precision--estimates of its effect would really just be guesses. In this case, the externality should be ignored--i.e., not considered at all--because if it were considered it would make the analysis appear more precise than it really is.

(True/False)
4.9/5
(39)

Superior analytical techniques, such as NPV, used in combination with risk-adjusted cost of capital estimates, can overcome the problem of poor cash flow estimation and lead to generally correct accept/reject decisions.

(True/False)
4.9/5
(31)

Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. This is just one of many projects for the firm, so any losses can be used to offset gains on other firm projects. The marketing manager does not think it is necessary to adjust for inflation since both the sales price and the variable costs will rise at the same rate, but the CFO thinks an adjustment is required. What is the difference in the expected NPV if the inflation adjustment is made vs. if it is not made?

(Multiple Choice)
4.8/5
(43)
Showing 61 - 73 of 73
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)