Exam 10: The Basics of Capital Budgeting: Evaluating Cash Flows

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(36)

An increase in the firm's WACC will decrease projects' NPVs, which could change the accept/reject decision for any potential project. However, such a change would have no impact on projects' IRRs. Therefore, the accept/reject decision under the IRR method is independent of the cost of capital.

(True/False)
4.8/5
(40)

Jazz World Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.

(Multiple Choice)
4.7/5
(37)

No conflict will exist between the NPV and IRR methods, when used to evaluate two equally risky but mutually exclusive projects, if the projects' cost of capital exceeds the rate at which the projects' NPV profiles cross.

(True/False)
4.9/5
(30)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(35)

Anderson Systems is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.

(Multiple Choice)
4.9/5
(26)

The IRR of normal Project X is greater than the IRR of normal Project Y, and both IRRs are greater than zero. Also, the NPV of X is greater than the NPV of Y at the cost of capital. If the two projects are mutually exclusive, Project X should definitely be selected, and the investment made, provided we have confidence in the data. Put another way, it is impossible to draw NPV profiles that would suggest not accepting Project X.

(True/False)
4.7/5
(39)

Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note that (1) "true value" is measured by NPV, and (2) under some conditions the choice of IRR vs. NPV will have no effect on the value gained or lost.

(Multiple Choice)
4.9/5
(42)

When evaluating mutually exclusive projects, the modified IRR (MIRR) always leads to the same capital budgeting decisions as the NPV method, regardless of the relative lives or sizes of the projects being evaluated.

(True/False)
4.7/5
(31)

Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

(Multiple Choice)
4.9/5
(38)

Projects A and B have identical expected lives and identical initial cash outflows (costs). However, most of one project's cash flows come in the early years, while most of the other project's cash flows occur in the later years. The two NPV profiles are given below:Which of the following statements is CORRECT?

(Multiple Choice)
4.7/5
(44)

Projects S and L both have an initial cost of $10,000, followed by a series of positive cash inflows. Project S's undiscounted net cash flows total $20,000, while L's total undiscounted flows are $30,000. At a WACC of 10%, the two projects have identical NPVs. Which project's NPV is more sensitive to changes in the WACC?

(Multiple Choice)
4.7/5
(40)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(32)

Cornell Enterprises is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.

(Multiple Choice)
4.9/5
(34)

The IRR method is based on the assumption that projects' cash flows are reinvested at the project's risk-adjusted cost of capital.

(True/False)
4.9/5
(49)

Which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(31)

Projects A and B are mutually exclusive and have normal cash flows. Project A has an IRR of 15% and B's IRR is 20%. The company's WACC is 12%, and at that rate Project A has the higher NPV. Which of the following statements is CORRECT?

(Multiple Choice)
4.8/5
(33)

McCall Manufacturing has a WACC of 10%. The firm is considering two normal, equally risky, mutually exclusive, but not repeatable projects. The two projects have the same investment costs, but Project A has an IRR of 15%, while Project B has an IRR of 20%. Assuming the projects' NPV profiles cross in the upper right quadrant, which of the following statements is CORRECT?

(Multiple Choice)
4.9/5
(40)

Thorley Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the WACC or negative, in both cases it will be rejected.

(Multiple Choice)
4.9/5
(32)

Masulis Inc. is considering a project that has the following cash flow and WACC data. What is the project's discounted payback?

(Multiple Choice)
4.8/5
(32)
Showing 41 - 60 of 107
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)