Most companies that use standards set them at

Free
(Multiple Choice)
4.9/5
(27)
Correct Answer:
Verified

A

The investigation of a materials quantity variance usually begins in the

Free
(Multiple Choice)
4.8/5
(46)
Correct Answer:
Verified

A

The total standard cost to produce one unit of product is shown

Free
(Multiple Choice)
4.9/5
(48)
Correct Answer:
Verified

C

The investigation of a materials price variance usually begins in the

(Multiple Choice)
4.9/5
(37)

The fixed overhead variance that indicates whether plant facilities were efficiently used is the

(Multiple Choice)
4.8/5
(46)

In a standard cost variance report,

(Multiple Choice)
5.0/5
(39)

A standard cost system may be used with

(Multiple Choice)
4.9/5
(44)

Under a standard costing system, manufacturing overhead costs are applied to work in process on the basis of

(Multiple Choice)
4.8/5
(36)

When a company implements a balanced scorecard approach in its business,

(Multiple Choice)
4.8/5
(40)

Standard costs

(Multiple Choice)
4.8/5
(41)

A materials quantity variance is calculated as the difference between the standard direct materials price and the actual direct materials price multiplied by the actual quantity of direct materials used.

(True/False)
4.9/5
(32)

EKPN Co.produces wooden boxes.The company's standards per box require 6 boards, each costing $10 per board, and half of an hour of direct labour.The standard labour rate is $15 per hour.In August, EKPN Co.Purchased 12,000 boards for a total cost of $123,000.It used 11,500 boards to manufacture 1,900 boxes.Total labour hours were 1,000 hours, and total labour costs were $16,250. What was the total labour variance for August?

(Multiple Choice)
4.9/5
(35)

The total overhead budget variance is equal to the

(Multiple Choice)
4.9/5
(39)

The formula for the materials price variance is

(Multiple Choice)
4.9/5
(43)

Labour efficiency is measured by the

(Multiple Choice)
4.8/5
(38)

A company uses 40,000 kilograms of materials for which they paid $9.00 a kilogram.The materials price variance was $80,000 favourable.What is the standard price per kilogram?

(Multiple Choice)
4.9/5
(45)

The direct materials quantity standard should

(Multiple Choice)
4.8/5
(41)

EKPN Co.produces wooden boxes.The company's standards per box require 6 boards, each costing $10 per board, and half of an hour of direct labour.The standard labour rate is $15 per hour.In August, EKPN Co.Purchased 12,000 boards for a total cost of $123,000.It used 11,500 boards to manufacture 1,900 boxes.Total labour hours were 1,000 hours, and total labour costs were $16,250.What was the material quantity variance for August?

(Multiple Choice)
4.8/5
(45)

Which of the following statements is FALSE?

(Multiple Choice)
4.8/5
(35)

A standard which represents an efficient level of performance that is attainable under expected operating conditions is called a(n)

(Multiple Choice)
4.8/5
(39)
Showing 1 - 20 of 113